Hydro-testing of drainage lines (Zones A & B) passed inspection. Fire Fighting
| Trade | Priority | Planned Activities | | :--- | :--- | :--- | | | High | Start VRF piping if units arrive. Complete Level 5 FAHU wiring. | | Electrical | High | Start pulling conductors for Levels 1-2. Install Light fixtures Level 3. | | Plumbing | Medium | Complete Roof RWP. Start Level 5 restroom rough-in. | | All | Critical | Clash resolution meeting for Level 6 ceiling space (Wed 8 AM). | mep work progress report sample
To maximize its value, an MEP Work Progress Report must evolve from a static PDF into a . In best practices, digital tools (like BIM 360 or Procore) link the report directly to the 3D model. A sample report in a digital format would include hyperlinks: clicking on "Chilled water piping – Zone 3" opens the exact BIM coordinates, showing a clash with an electrical tray. Furthermore, attaching daily photo logs turns vague text into verifiable evidence. A picture of a completed riser with a pressure gauge reading 150 PSI is infinitely more valuable than a line item stating "Riser tested." Hydro-testing of drainage lines (Zones A & B)
MEP Progress Report for Hotel Pawan Palace - Plumbing - Scribd | | Electrical | High | Start pulling